FYPPGBank Project Title Approval Menu Guideline

 

Step 1- Head over to FYPPGBank System using this link https://fyppgbank.apu.edu.my/jw/web/login and log in using your APKey.

image-20240919-034908.png

 

Step 2- After logging in, click the FYPPGBank icon to navigate to the main page.

Joget1-20240919-035024.JPG

This is FYPPGBank Main Page view

 

Step 3- Click on Project Title at the left sidebar menu and click on Student Pending Approval proposal Project Title.

 

Step 4- It will take you to the page where you will see the table Student Pending Approval Proposed Project Title

 

Step 5- Click on the “PM Approval” to approve the project title

 

 

Step 6- You have to fill out all the required information to submit it

Test Case 1: If you want to have the Project title reverted this is the process

 

1- If you revert you have to submit it

 

Step 7 - Click on the “Submit” to revert the project title

 

 

Step 8- You have to fill out all the required information to submit it

 

Test Case 2: If you want to have the Project title approved this is the process

1- If you approve another table will appear

Step 9- You have to fill out the information in the new table that will appear information in the new table that will appear

 

Step 10- Click on the “Submit” to approve the project title

 

 